    Hi, hope there's room for yet another SX2 CNC conversion thread. I bought the LMS Hi Torque 3900 mini mill over a year ago and am very happy with the machine. I always wanted/planned to convert it to CNC, but with no machining skills (at least not metal, lots of woodworking) it took a long time to learn the basics and get enough tooling in place to do anything serious. After reading and learning from the many build threads here, I also need to thank Hoss, DJBird, and many others on this forum--without their excellent work I wouldn't have known where to start. Anyway, this is going to be a sort of "catch up" thread as I am pretty far along on the build. I didn't do very well on documenting while I was doing the build, so I've been doing some catch-up, taking a lot of pictures and will cover what I've done to date, and then to completion of the project. The picture is of my mill, when it was brand new and clean, mounted on it's dedicated bench/flood table.
    Attached Thumbnails Attached Thumbnails IMG_4861s.JPG  

  2. #2
    Join Date
    Nov 2012
    Posts
    174

    Bench buildup

    The first thing I did after getting the mill (and doing some playing around of course!) was to build a solid bench. Probably jumped the gun but I decided to build a flood table from the start. I almost didn't allow enough room side-to-side to allow for the X-axis stepper, but it looks like it will work out. The finished product will have a angle aluminum uprights and 24" plexiglas sides. The bench is pretty sturdy, with a 1.5" plywood top (two layers of 3/4" plywood) on 2x4 and 4x4 frame. The outside was eventually skinned with 1/2" plywood. The pedestal for the machine is placed offset to the left to allow for the x-stepper motor. Once the pedestal was in place (made of several layers of 3/4" ply), I located and drilled the drain holes and added the stringers and masonite panels to make the sloped surfaces. The top was then covered with overlapping flashing aluminum to provide a sturdy surface. The aluminum was secured with contact cement, and clear silicone calk along the seams. I have yet to run a drop of coolant even though the pump and lines have been run, but hopefully soon! The attached show some of the table construction details and the nearly finished product. I later added the remaining sheet and some aluminum angle around the border to form the bottom for the eventual side walls.
    Attached Thumbnails Attached Thumbnails IMG_4784s.JPG   IMG_4787s.JPG   IMG_4789s.JPG   IMG_4788s.JPG  

    IMG_4784s.JPG   IMG_4822s.JPG   IMG_4856s.JPG  

  3. #3
    Join Date
    Nov 2012
    Posts
    174

    Development plans

    Ok, with the machine mounted on a suitable work bench, the next thing was the CNC development plan. A primary goal was to do as much of the mill work on this machine for the conversion as possible. Keeping that in mind, here is the rough CNC conversion design plan:

    1) Use the proven X,Y ball screw conversion demonstrated by Hoss’s X2 and many others subsequently. Since the saddle needed to be modified to fit the x-axis ball nut, this would require a spare part to be purchased in order to do that machining on this mill.

    2) For the Z-Axis, I went back and forth many times trading off the CNC fusion side-mount vs. a more centrally located lift point design for the Z-axis ball screw. I’ve seen a couple of centered designs; one uses a small diameter ACME or ball screw with the nut mounted inside the carriage approximately where the pinion drive shaft normally passes through. The other popular centered design is the StirlingSteele and Hoss rotating driven ball nut that secures the screw to the top of the carriage and uses a combined drive pulley, ball nut and bearing to move the carriage. The centered design finally won out as I really prefer the look and mechanical balance it seems to afford. This isn’t a knock on the cncfusion kits, PLENTY of those out there working fine, just my personal choice. From the two center mount choices, I decided to attempt the embedded ball nut approach, figuring that if I failed I could always fall back to the other proven design. Either of these designs is complicated by the far back positioning of the spindle motor near the column. In order to modify and make parts for the carriage, I would also need a spare carriage part.

    3) Identify the basic mechanical components such as ball screws and nuts,
    belts, pulleys, motors, and shaft couplers and sources for each.

    4) Develop some CAD 3D models to assist in designing the mechanical parts and selecting specifics of the mechanical parts such as bearings, etc. for the X,Y and especially the Z axes. Develop shop prints (well, not really, but good enough for the garage shop) to make the parts.

    5) Identify the necessary tooling. After I bought the mill, I had a pretty strict budget for tools so I carefully selected a number of key components to stay within budget but still give good functionality. The essentials were: 3” vise, R8 collet set, end mill set, 115 piece drill bits, boring head and bars, 6” caliper, 1” micrometer, 1” dial indicator, .030” test indicator and holder, and drill chuck as the LMS mill doesn’t come with one. Other tooling needed would be purchased along the way to spread out the costs.

    6) Electronics -- Identify motors and controllers, breakout board(s) and a computer to host Mach3. After searching and comparing prices, I narrowed the suppliers for these components down to either Keling or Probotix. Both have good offerings, but in the end I like the bipolar drivers and hybrid motors from Keling a little bit better. I still plan to buy a relay board to control flood coolant pump from Probotix, they have some nice options. I have an older but capable laptop with a docking station with a parallel port so that will be the Mach3 host.

    7) Additional Considerations—Most people with the tilting head mills have added some sort of column support to add some rigidity to the system. My plan added a length of 4” steel C-channel to the back of the column to boost its cross section, and also to add some triangular gusset braces between the column and rear base castings. Another area for consideration is the completion of the enclosure, the access openings, placement of the electronics controller, and the wiring scheme, including limit switches.

    So that's the plan, much of this has been completed so I'll start posting the design and build details next.

  4. #4
    Join Date
    Nov 2012
    Posts
    174

    Z-Axis – Spindle Carriage Modification

    I decided to tackle the hardest part of the build first, namely the Z-axis. To get started with the effort I purchased the replacement part for the spindle carriage, i.e. the part that has the dovetails and is bolted to the spindle box. Fortunately LMS stocked this part for $65+shipping. Wished it were less, but I couldn’t proceed without it so ordered it and had it in a few days. The first order of business was to clean up the inner casting outlines at the back side opening (dovetail side) so that an insert would have straight edges to fit into. Also worked in from the wider opening (front) side to clean up the shoulder features and basically flatten and straighten up things a bit. Because the casting inner walls aren't parallel to the outside, no attempt was made to do anything with the sides, just the bottom areas where an insert block would be made to fit down against those surfaces. Once the part had at least some flat and parallel areas to work with, careful measurements of the features were made a 3D CAD model was developed. The column was also modeled and by placing the two models together the available spacing and design of the ball nut carrier were much easier to visualize. A 3D model for the ball nut was located on the RBS website, and that allowed orienting and positioning the ball nut for the best fit in the available space. Since there is a 16mm hole in one side for the rack shaft, that was convenient to use as the method to hold the insert. The hole on the opposite side was to be enlarged to match, and a pair of 16mm shoulder bolts would serve as the main fasteners for the ball nut holder. The smaller hole located forward and down would be re-drilled and copied on the other side to provide a second attachment point using some ¼”-20 button head screws.
    Using the 3D CAD features, the amount of space available for a ball screw could be accurately estimated, and a model of a shaft opening was developed into the part. The attached rendering gives an idea of what the model provides. I didn't do a complete model, only as much as was needed to determine if it was going to work, and what would need to be done to make it work. Playing with the model, it was clear that while there is almost enough room for a 5/8" ball screw to pass behind the spindle motor, the bearing block to support it would need to be located at least the height of the motor (6 - 8") above the top of the column in order to allow the motor to not interfere with the bearing at the top of its travel. That wasn't an attractive solution, so the unavoidable solution was to move the motor forward. This turned to be simpler than expected, as the modification only required about 1/2" of movement to get the needed clearance.

    The attached pictures are of the last model updates including the Z bearing block, which will be covered in detail later. If you look closely at the wireframe you can just see the ball return tube of the ball nut model.
    Attached Thumbnails Attached Thumbnails Z Axis Assembly 1.jpg   Z Axis Assembly 2.jpg  

  5. #5
    Join Date
    Nov 2012
    Posts
    174

    Z-Axis Carriage Machining

    These pictures show some of the final work being done on the spindle carriage to cut the ball screw pathway through the carriage and the baall nut insert at the same time using a 3/4" ball end mill. The carriage was aligned to the x-axis of the mill using a dial indicator along the dovetail. The aluminum insert/ball nut carrier can be seen fitted into the middle. I'll show more details for the ball nut carrier in the next post.
    Attached Thumbnails Attached Thumbnails IMG_5640s.JPG   IMG_5642s.JPG   IMG_5643s.JPG  

  6. #6
    Join Date
    Nov 2012
    Posts
    174

    Z-Axis Ball Nut Carrier

    These pictures show the completed ball nut carrier insert and the ball nut fitted into the carrier. To make that carrier was a lot of work. The first part involved fitting a chunk of aluminum into the carrier housing. I began by marking out the areas and depths that would need to be removed to clear the shoulders in the bottom of the carriage. These were just approximated and then many, many test fits and removing of material until it fit down into the opening and flush with the back surface. Once that was complete, the shoulder bolt holes were drilled and tapped to 10mm x 1.0mm. The insert was installed into the carriage with the shoulder bolts (giving an appropriate Frankenstein look), to get ready for the ball end mill cuts to make the ball screw shaft as shown in the previous post. When this was completed, the cut out for the ball nut was made with the same setup. Here a 1” 5-flute end mill was used to make a 1” channel centered on the ball screw channel, and 1” deep, with length equal to the length of the ball nut. Then the insert was removed and rotated upright so that the 1” cutter could cut down from the top side into the channel to square up the end of the channel. When completed, this left the inner corners of the ball nut channel with fillets in the bottom corners that needed to be removed. I used a smaller end mill to remove more of the material, and in the end just scraped and chiseled out the remaining bits of material. A sharp 5/16” HSS lathe tool bit shaped roughly like a chisel was used to do some of the work. Finally, since the ball return tube faces downward, an end mill slightly wider than the ball tube was used to make a channel for that feature, and also made some plunges to accommodate the screws and the metal clamp. It just took a lot of patience but finally got it done. By this time I was wishing for a CNC machine to make this part! If I did it again, I would simply drill 1/8” holes centered in the corners for the ball nut to eliminate the need to make sharp corners.
    Attached Thumbnails Attached Thumbnails IMG_6170s.JPG   IMG_6171s.JPG   IMG_6176s.JPG   IMG_6181s.JPG  

    IMG_6179s.JPG  

  7. #7
    Join Date
    Nov 2012
    Posts
    174

    New Spindle Motor Plate

    As previously discussed, the spindle motor needs to move forward by about ½” to accommodate the ball screw and to clear the Z-axis bearing block. It turns out that there is enough room in the drive belt cover cutouts to accommodate the movement without any other changes, so I decided to make a new motor mount plate that would continue to use the rear two holes and would essentially stretch forward by ½” , thereby requiring only two new holes to be tapped closer to the drawbar opening. There is a large round cutout in the middle of the steel motor plate, otherwise it is a pretty simple part. I had access to a 6” rotary table, so that provided a solution for making the big hole. The steel thickness is a little less that ¼”, so it was easy to buy some ¼” x 4” steel for the raw material. After cutting a piece to length and facing both sides down to the nominal thickness, the layout consisted of using Dykem and then tracing the old motor mount at one end, including the large hole, then moving it to the other end and tracing the motor mount slots, and ready to machine. The mounting slots were cut first, then the plate was put on the rotary table. I used a conical center finder to center the mill in Y first by picking up the scribed arc and dividing the distances and cranking the to the center in Y and locked the axis. The X-axis was cranked to pick up on the scribed circle, then moved back by the diameter of the cutter (3/8”). There is a small amount of clearance for the motor so it wasn’t super critical. I did at one point early on move back by 7/16” and used that sized end mill to plunge completely through the part. Then the table was moved back and the 3/8” end mill was used to finish cutting out the hole. The larger hole allowed for a place where the movement could stop without generating chatter (allowed for clearing off the chips) and where the end mill could be lowered into the hole before starting the next cut. With a stiffer machine it might make no difference, but it seemed like a smoother operation on this machine using the relief hole.
    I installed this plate and used the mill with the shorter spindle drive belt with no problems. The shorter belt is a HTD5-330-15 that I got from Timing Belt Pulleys Taper Bushings Timing Belts Belt & Chain Tensioners Tension Testers Diametral Pitch Gears Gearheads. Later, when I disassembled the machine to do the final CNC installation, my machinist friend (actually his son) used a ¾” end mill to make the cutouts in the end of the motor plate and the pulley cover to accommodate the ball screw pass-through. I need to acknowledge my machinist friend RT, he has always been patient and quick to help out with expert advice and some occasional machining to support this project—Thanks RT! (and son!).
    Attached Thumbnails Attached Thumbnails 2012-05-12_14-12-43_873s.jpg   IMG_6197s.JPG   IMG_6194sss.JPG  

  8. #8
    Join Date
    Sep 2012
    Posts
    1543
    Great build! Great Pictures and I love the bench!

  9. #9
    Join Date
    Nov 2012
    Posts
    174
    Quote Originally Posted by BAMCNC.COM View Post
    Great build! Great Pictures and I love the bench!
    Thanks! Lots more to come.

  10. #10
    Join Date
    Nov 2012
    Posts
    174

    X, Y Axis Bearings and Motor Mounts

    By this time I wanted to get started on the X and Y axis ball screw details, but I couldn’t start working on those until the X,Y bearing details were figured out. I spent a lot of time trying to decide on the axis bearings, and had even bought some of the thrust type bearings thinking at one point that I had it settled. Then I saw where a lot of setups were using angular contact pairs. In the end, I got realistic, stopped over thinking it, and settled on using double row angular contact bearings. These have the additional advantage of being sealed units too. I bought a bearing from vxb.com to measure for use in the CAD design. The unit is a 5200-2RS (10mm x 30mm x 14.3mm) double row angular contact bearing. Although not rated as high for load carrying capacity as a pair of ACs, these seemed to be adequate in my estimation for this size machine and the forces it will generate on these axes. With that finally decided, the designs for the bearings were pretty easy. The Y bearing block assembly is basically a modified Hoss design with a spacer and the bearing block. The X bearing block assembly consists of a new table end piece with the bearing block attached. The bearing blocks consist of two pieces: a bearing holder and a lid. Both the holder and lid are designed with recesses for shaft oil seals, although since the bearings are sealed these will probably not be used. This is a typical design that you will see described at 5bears.com and other places. This design calls for the bearing recess to be a couple thousands shy of the true bearing width to allow the lid to apply some load to hold it in place. Shims can always be used if the machining doesn’t accomplish this so no worries there. The motor mounts were inspired by djbird’s design that uses two flat plates for the motor mount. This gives a nice appearance of a one piece design and also provides some motor heat sink as djbird mentions. The attached are some of the CAD drawings that show the general design and a rendering of the Y axis. I couldn’t find the X axis rendering but you get the idea. In the next section I’ll cover how these were made.
    Attached Thumbnails Attached Thumbnails Y-Axis Bearing Assembly.jpg   Y-Axis Bearing Assembly 3D.jpg   X-Axis Bearing Assembly.jpg  

  11. #11
    Join Date
    Jan 2009
    Posts
    484
    Nice work! I'll be reading along..... superb so far!
    Q: How many tools does it take before a simple task becomes a project?
    A: Just one. I'm the Tool that turns a simple task in to a project.

  12. #12
    Join Date
    Nov 2012
    Posts
    174
    Quote Originally Posted by TroyO View Post
    Nice work! I'll be reading along..... superb so far!
    Thanks TroyO!

  13. #13
    Join Date
    Nov 2012
    Posts
    174

    Making X, Y Axis Bearing Assemblies

    The stock for the X axis bearing main block 1” x 3” x 3” aluminum, the lid is made from 3/8” x 3” x 3” aluminum, and the end bracket starts with a piece of ½” x 3” x 6” aluminum, all 6061 alloy. The first operation was to face the block and lid materials to finish thickness. The pieces were then rough cut within .1” of finish size on a bandsaw and then milled to .020 oversize to allow for a final cleanup later. Following a tip from the excellent book “Machine Shop Trade Secrets” by James Harvey, the lid and block were held in the vise together and machined to size at the same time, assuring that they came out identical. Throughout machining the two parts were marked so that they maintained the same mating surfaces and orientation also. Once milled to size, the drill locations for the various holes were laid out, excluding the motor mount holes. The motor mount holes require a precision alignment that will be performed after th bearing block is completed. All of the through-holes were drilled, and then the tap drill is used to drill through the lid and into the block for the tapped holes in the block. The lid is then removed and the holes in the block tapped. This is a tedious process, at least the way I did it. I used the center finder on each hole to align the spindle, then used a spring loaded tap guide held in a collet to help align the tap while it is starting. Use cutting oil or tapping oil to make clean cuts. After finishing the tapping, the lid was put in the vise and the tap holes enlarged to the proper clearance values. At this point I screwed the lid to the block and checked the fit, adjusting to make the outside edges align as well as possible. Mine didn’t align perfectly, but no matter as they were .020” oversize for that reason. With the parts firmly screwed together, I mounted the unit into the 4-jaw lathe chuck. The idea is to then center the part and then carry out the boring process. Well, this was a new skill for me and took a good long time to get the independent jaws tight and adjusted. The digital dial indicator was placed so that it would reach down onto the part from the top. After centering the part by eye, I set the indicator on the top surface, zeroed the indicator, then carefully rotated the chuck (lifting the indicator stem of course!) to get a reading on the opposite face. The adjustment to be made is half of this reading, and in the direction opposite of that indicated, so tighten/loosen the jaws to achieve that value on the indicator, and then repeat the process. Once that pair of edges is within a couple thousandths of center, do the same for the other two surfaces. Then fine tune down everything to a thousandth or less. Sounds pretty simple, and it is, but it takes a little practice. Maybe there is a better way, but this did work. The next step was to center drill and then drill up to 3/8”, all the way through. The idea is to bore the smallest common hole through, and then finish each part separately. The initial boring operation saves time by cutting two in one setup. The bore could also be used as another way to center the part using a dial test indicator, which I did on the second bearing assembly. After boring through the smallest common hole, the lid was removed, and unfortunately the centering operation needs to be run again (!). After that, the bearing pocket is the next operation. Since the tolerance of the pocket depth is desired to be held to 0.001”, I used the digital dial indicator located against my carriage. I zeroed the indicator with the boring bar touching the face of the part, and then moved the boring bar into the existing center bore. The carriage was then moved over to about .005” short of the final cut depth, and the carriage stop was locked at this position. The carriage stop allows for faster cutting without constantly looking at the dial indicator. In fact, the indicator can be removed if desired until the finishing cuts need to be made. Take care to hold a tight tolerance on the pocket diameter too. You should use a bore gauge to monitor the progress. I also kept the bearing at hand and made a lot of small cuts to sneak up on the final diameter. You should debur the edge of the hole before test fitting the bearing, as the bur will fool you into thinking the hole is too snug, and apply a little oil. I was able to get my pockets to about .0015” oversized so the bearings are nice and tight. After finishing the bearing pocket, the part is removed and turned around to cut the oil seal, and yes, another centering operation is required, but it’s getting easier each time. Finally, it’s the lid’s turn in the 4-jaw to bore out the center hole and make the oil seal pocket. Here, only one centering operation is needed. These operations are the same for both the X and Y bearing blocks. Each has its own bolt patterns, but the center bores and oil seal features are the same. The table end bracket for the X axis was cut and milled to length (left oversize .050) but left as a rectangle until the bearing block was completed and attached. I found that the end bracket from the opposite end of the table when kept in the same orientation but moved to the crank end of the table fit with the same top clearance and fit the bolt locations, so I used this as a pattern to transfer the two table fastener hole locations and also the shaft hole center. This would ensure that the new ballscrew shaft center height relative to the top of the table would be the same at both ends of the table. The table holes were drilled and counter-bored in the bracket, and the shaft hole was drilled to the slightly oversized dimensions to allow for some alignment tolerance. The bearing block was not attached to the bracket until the X-axis ball screw was completed to allow for a near perfect alignment of the bearing block onto the bracket. This was accomplished by sliding the bearing block onto the shaft, aligning the block for vertical/horizontal, and then using a transfer punch to mark the locations on the bracket for the tapped holes. After that, the bottom of the bracket was cut and milled flush with the bearing block, and the tapers were cut along the bottom bracket at the same angle as the original brackets, which is only for appearance.
    The Y bearing block assembly is made in a manner very similar to the X axis assembly. The Y spacer block and bolt patterns are taken directly from Hoss’s drawings, and I verified that my base had identical tapped hole placements and the shaft holes were well within the clearances. Anyone doing the conversion should verify the hole locations before making parts to match.
    For the materials used to build up the X and Y bearing assemblies, I used vxb.com to source the bearings, and found a great place for the oil seals at bestpartsonline.com. I bought the fastener hardware at boltdepot.com. The metal came from speedymetals.com. I did need to buy some additional tools for this effort, including a 4-jaw 3” chuck for the mini-lathe, and a set of transfer punches, all purchased at shars.com.
    *** Sorry for the long post, didn't realize how long it was getting, I'll try to keep it shorter or break it up going forward.
    Attached Thumbnails Attached Thumbnails IMG_6281s.JPG   IMG_6283s.JPG   IMG_6248s.JPG   IMG_6276s.JPG  

    IMG_6246s.JPG  

  14. #14
    Join Date
    Nov 2012
    Posts
    174

    Ball Screw Selection

    Early on, prior to buying the mill, I bought an 18” length of ball screw made by Rockford Ball Screw (RBS) from Automation4Less.com so that I could assess whether I could learn how to machine the ends of the ball screws, and if my little 7x10 HF mini-lathe would be up to the task. I’ve seen mixed opinions on this, but decided to give it a try. After having a pretty hard time, and consulting my machinist friend several times, I finally was able to get a decent 10mm journal and even cut some metric threads (10 x 1.0 mm). I had to resort to grinding off the hard threads, which was a nasty, dirty job as I don't have a dust trap system on my bench grinder. Still, the RBS screws seemed to be a satisfactory choice and it was very easy to order them. Or at least it used to be. For whatever reason Automation4Less dropped the RBS screws by the time I bought the mill, so I had to decide whether to stay with those or change to Roton or some other brand. To be truthful, the machining for the one screw I had already done was so unpleasant that I wanted to minimize the number of additional pieces I needed to turn, so I contacted RBS directly and they were very easy to work with to get two additional 2’ lengths of 5/8” ball screw and the 3 square ball nuts I needed. I also requested that two of the nuts be pre-loaded with oversize balls for reduced backlash (they can’t do the oversizing without the screw, so I had to order one standard nut for the piece I already had). Note that these ball nuts appear to be nearly identical to those sold by Roton, Thomson, Nook, and McMaster-Carr. The RBS screws have the black oxide coating however. The comment I will make on the RBS screw quality is generally good, however one of the 2’ lengths was not as straight as I would have expected. I discovered this after I had already cut a piece for the Y-axis. Since the Y-axis is a short length of screw, that helped to reduced the error significantly, but it still required some straightening. Had I realized it before cutting I would have exchanged it for another piece. Given the experience I’ve had with RBS, I believe that they would have exchanged it without issue. I’ll post the end machining details in the next post.

  15. #15
    Join Date
    Nov 2012
    Posts
    174

    Ball Screw Machining (Part 1)

    With the X,Y bearing block and mounts finalized, the ball screw journaling details were established, so I got ready for the torture of turning 2 more ball screws. In the initial attempt, the tools were mostly brazed carbide tools of the 3/8” shank BR variety. Several of these were broken as the tool dug in and made a loud bang—not pleasant. They also needed frequent re-sharpening. A triangular 3/8” shank insert tool with C2 carbide inserts quickly broke or lost their edges too. My ignorance of proper cutting angles and amateur grinding skills were likely part of the problem, however my experiences seemed to be worse than others’ I’ve seen. I looked for other inserts for the 3/8” tools, and bought some TiN (gold color) inserts, and also some TiAlN inserts (shiny black color, EM YBG202) from Shars. I followed Hoss’ example and made a split collar to center and protect the ball screws, although the 3-jaw 3” chuck is too small to pass it into the spindle so it is much shorter. However, it still worked well. Additionally, a slip fit Delrin plug was turned for the opposite end of the spindle to keep the screw from whipping. Started turning the next ball screw with some new, sharp brazed BR tools and immediately broke one. Then tried the TiN inserts and found they would hardly cut at all. About this time I found what was causing most of the problems I was having with the cutters digging in and breaking. Not adjusted properly, the carriage had a small amount of vertical play that was allowing the cutting tool to move very slightly when a heavy load was applied. The movement caused the tool to rotate deeper into the cut, causing it to bind up, chatter, and either break or stall the machine. The carriage was tightened, and the BR carbide tools began to make consistent cuts. The TiAlN inserts were tried next, and man, what a difference. These inserts are very sharp and tough and they really cut well. I couldn’t believe how easily these inserts were cutting that hard stuff. Now it only took a few minutes to cut through the case hardened layer, and these inserts leave a nice finish too (look at the bushing support journal of the x-axis --this is the raw machined finish!). The cutters do wear out fairly quickly though; the swarf is very abrasive and hard to keep clear from the cut so it tends to wear down the cutting edge. I tried to keep it brushed off, but it tends to stick in the cutting oil. A flood coolant setup to keep the swarf flowing might help the inserts to last a lot longer. I think it took 1 insert (3 points) to get through the threaded area, and one more point on a second insert to complete the roughing. At about $4 per insert, this is maybe a little pricey, but well worth it. The ball screws were roughed down to within .015” or so of the final size, then switched to a HSS tool fashioned like that recommended at 5bears.com for the finish cuts. I stopped at about .001” to .002” over size and carefully sanded them in for a tight slip fit in the bearings. On the first ball screw I used an E-style triangular insert cutter to cut threads with satisfactory results. For the last two screws I bought a thread cutting tool that uses a thread cutter insert to cut the threads. This produces better threads and cuts very cleanly.

  16. #16
    Join Date
    Nov 2012
    Posts
    174

    Ball Screw Machining (Part 2)

    After finishing the journals, the screws were cut to length with an air driven cut off wheel. The screw was chucked in the lathe and the cut-off tool zip-tied the cross slide. Set the lathe to a slow turn rate, and feed the cutting wheel into the screw with the cross feed until it parts. I put a wet cloth beneath the cut to protect the lathe ways from the swarf. (When turning I also used those heavy blue paper shop towels secured with some small round magnets to catch the swarf during machining.) The final operation was to adopt an idea mentioned on this website (Will's Mini-mill), but mine is a removable fitting to bolt onto the end of all of the ballscrews to assist in loading and unloading the ball nuts onto their cardboard tubes. This is made from 5/8” CRS, but aluminum should work ok too. The retaining screw is a ¼”-20 button head, and the non-bearing end of each ball screw is tapped ¼”-20 about 3/4” deep. The smaller diameter section of the fitting makes a slip-fit onto the ball nut cardboard tube, making it easy to slip the ball nut on/off the screw without worrying about holding the tube against the end—one slip and the bb’s go scattering. It works great, but make sure to tighten the screw before removing a ball nut so that it doesn’t unthread while removing the ball nut—the voice of experience.

    Commentary: If I did this over I would change to 12.0mm bearing journals and 12.0mm x 1.25mm threads as this would require less material removal, and nearly the same size bearings are available with 12mm ID as for the 10mm versions (e.g. 5201-2RS). I wasn’t sure when designing the bearing blocks whether a 12mm diameter would be below the case hardening layer which would complicate threading, but it seems that it is, so threading wouldn’t be a problem.
    Attached Thumbnails Attached Thumbnails Finished Ballscrews.JPG   Finished Ballscrews zoomed.JPG   Finished X-Axis Ballscrew Bushing Support End.JPG  

  17. #17
    Join Date
    Nov 2012
    Posts
    174

    Ball Screw End Fitting

    Some pictures of the ball screw end fitting to help install/remove the ball nuts.
    Attached Thumbnails Attached Thumbnails End Fitting.JPG   End Fitting Ball Nut Install 1.JPG   End Fitting Ball Nut Install 2.JPG   End Fitting Ball Nut Install 3.JPG  

    End Fitting Ball Nut Install 4.JPG  

  18. #18
    Join Date
    Nov 2012
    Posts
    174

    Saddle, Table Modifications, X, Y Axis Ball Nut Holders

    As planned, I bought a replacement saddle from LMS for $65+shipping. They do a good job keeping parts in stock. Although I can’t completely justify it, at this point I also purchased another base (and another $65 spent) so that I could completely fit up the Y-axis, and by removing the two screws from the X axis bracket and sliding the table off of the mill, Icould mock up the entire X,Y assembly independently of the mill without much effort. It also allowed me to get the new saddle and base working smoothly together prior to the final machine teardown and CNC buildup. I went ahead and also bought a new set of x,y, and z gibs from LMS too. After making some measurements and determining the height of the ball screw, the usual material was milled out of the saddle to allow the ball nut and the ball screw to pass through. The measurements showed that only a small amount of material would need to be removed to allow the ball nut to be in position vertically, maybe .020”. The cast iron mills easily and so this didn’t take long.
    The X and Y axis ball nut holders are now very commonly seen parts in the many X2/SX2 builds, but for completeness I’ll post my copies. These are pretty much to Hoss’ prints, slightly wider and a little beefier to fit the SX2 slots. These are made from 7075 aluminum, only because I had some scraps available. The scraps were round stock, so it took a little more machining (the radius was built-in for the top of the X-axis holder) but I needed the practice anyway. End mills were used to plunge out the holes to ¾”, then ran a Silver&Deming 7/8” drill bit, then tapped with the 15/16”-16 tap (bought this at wttool.com). I didn’t have a large enough tap wrench so I used two end wrenches, and also the spring tapping center held in a collet. All steps were done with the same setup to keep alignment, but this operation was almost beyond the vertical reach for the mill, and I had to remove the stop block that keeps from running the mill off the rack to get the extra movement needed. When installing the nuts I shimmed between the nut and the holder to get the nut to be tight in the orientation I needed, and then installed nylon tipped set screws per the drawings.
    In doing the X axis ball nut fit-ups, it became apparent that the wide, shallow machined slot on the underside of the table wasn’t quite wide enough to clear the ball nut and would bind up in different spots. Since I had no way to mill it, I used a dremel with a grinding wheel to knock off the corners of the machined slot, basically putting a chamfer on at 45 deg. This worked, but the clearances were still tighter than I liked, so later on, when the mill was dis-assembled I took the table to my friend and had the slot milled a little wider and a little deeper so I could stop worrying about it.
    Attached Thumbnails Attached Thumbnails IMG_5753s.JPG   IMG_6250s.JPG   IMG_6269s.JPG  

  19. #19
    Join Date
    Nov 2012
    Posts
    174

    Column Top Insert and Stiffener

    I wanted to beef up the column, as much for appearance as function so I settled on some 4” x .187 steel channel. I bought a 2’ length at a local machine shop, but since I couldn’t machine this length, I took it to my friend to face mill the sides and bottom. He did a great job, but this material was far from flat and was not easy to fixture and keep from chattering. Lunch was definitely on me for that one. The column outline was traced onto the channel and cut to match, but I needed to use a bigger machine to cut the large pivot hole. The stiffener was clamped to the column and a pattern of 1/4"-20 holes were drilled and the column tapped, and the holes in the channel opened up for clearance.
    The insert in the top of the column is a chunk of aluminum cut to fit down into the column by approximate 1.5” to provide a solid mount for the Z-axis bearing block. This took a lot of effort to make, and is probably not the best way to go, however since I started it I just kept going till finished. This would definitely be re-designed if done over. The insert was clamped down tight and the holes drilled with the ¼” tap drill, then separated for the tapping. The channel and column holes were then enlarged to clearance size as necessary. This approach ensures great alignment and fit of the screws. Assembly uses ¼”-20 button head socket screws. I had ¾” length screws on hand so that’s what I used throughout.
    The pictures show the insert finished while the mill was together, and then later attached to the column as part of the assembly with the stiffener. I also had the insert milled perfectly flush with the column at this point since it was made a little oversized to allow for finishing.

    Edit: Note that the column insert is primarily there so that the spindle belt/pulley cover can rise above the height of the column and allow the spindle to rise to completely to the top of the column before meeting the Z bearing block. You can see that in the second picture.
    Attached Thumbnails Attached Thumbnails IMG_5756s.JPG   IMG_5759s.JPG   IMG_6212s.JPG   IMG_6206s.JPG  

    IMG_6205s.JPG  

  20. #20
    Join Date
    Nov 2012
    Posts
    174

    Stepper Motors, Controllers, and Breakout Board

    As mentioned in the design plans posting, I decided to go with Keling for motors and electronics. Overall their price was a little better than Probotix, but it was close. Here’s what I bought for a little under $400:

    1 x KL23H286-20-8B 381 oz-in stepper dual shaft
    2 x KL23H276-30-8B 282 oz-in stepper motor, dual shaft
    3 x KL-4030 Stepper Driver
    1 x KL-350-36 36V/9.7A power supply
    KL-DB25 Breakout Board

    The motors are NEMA 23 frame and I picked the dual shaft versions for two reasons: 1) it would allow manual use if desired by attaching a handle (I know, probably never happen, but us newbies need to have the option like a security blanket) 2) In the future I would like to look at adding encoders to the motors to support closed loop (servo) control. I recently was reading about the DynoMotion KFLOP controller, and it has the capability to close a servo loop around steppers that have an encoder installed.
    I also started looking for motor shaft couplings and it seems that the overall consensus is to use the Oldham style. I bought one unit from McMaster-Carr and it is very nice but a little pricey ($28) so I gave Amazon a try. I found what I thought were Oldham half couplings for about $5 each so I ordered 2 pieces for each side (5/16 for ball screw side, ¼” for motor side) and some of the spacers. These are the clamp type instead of set screw. When the order came there were four complete couplings in the bag, 2 @ 5/16” on both sides and 2 @ ¼” on each side and including the spacer. The bags have part numbers from smallparts.com and apparently they were dumping these (Huco mfr.) couplers so I got some extras out of the deal, just needed to swap parts to make the coupling I needed, and all for $26 with free shipping.

Page 1 of 8 123

Similar Threads

  1. Mini-Mill CNC conversion kit?
    By arrio in forum Benchtop Machines
    Replies: 2
    Last Post: 07-12-2012, 09:46 PM
  2. Mini Mill Conversion Question
    By jjwl89 in forum Benchtop Machines
    Replies: 15
    Last Post: 12-25-2005, 11:01 PM
  3. mini mill conversion- which way would you go
    By cnctoolman in forum Benchtop Machines
    Replies: 30
    Last Post: 04-15-2005, 12:52 AM
  4. help with mini mill conversion...
    By Gnome in forum Stepper Motors / Drives
    Replies: 6
    Last Post: 01-27-2005, 01:48 AM
  5. Mini-Mill Ballscrew conversion?
    By rustyolddo in forum Benchtop Machines
    Replies: 2
    Last Post: 07-29-2004, 04:22 PM

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •